Open Access

Table 8

SPP (PWR 2748 MWth → 1000 MWe): electricity cost.

Reference core thermal power (MWth) 2748
Reference electric power generation capacity (MWe) 1000
Specific construction cost ($ per installed kWe (electric power)) 4101.51a
Specific fuel cost ($ per produced MWeh (electric power)) 9.33a
Specific O&M cost ($ per produced MWeh (electric power)) 14.74a
Specific decommissioning cost ($ per installed kWe (electric power)) 820.30b
Length of the construction period (years) 7a
Economic lifetime of the plant (years) 60a
  Average availability of the plant (%) 85a
Length of the decommissioning period (years) 5
Discount rate (%) 5
Cost of electricity (10−2 $ per kWeh) 5.816
   Percentage allocated to construction (%) 58.15%
   Percentage allocated to fuel (%) 16.04%
   Percentage allocated to O&M (%) 25.34%
   Percentage allocated to decommissioning (%) 0.46%
a

Values suggested in the OECD' 2010 Projected Costs of Generating Electricity [9, p. 103].

b

20% of the specific construction cost.

Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.

Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.

Initial download of the metrics may take a while.