Table B.2

Reactor costs.

Item Unit Reactor type Range Basic value
Overnight construction cost US $/kW(e) VVER SFR 3500–6300 4000
3600–6600 4400
Fixed O&M cost US $/kW/year VVER, RBMK SFR 60–87 70
65–92 75
Variable O&M cost US $/MW h VVER, RBMK SFR 0.8–2.7 1.14
1.1–2.9 1.16